Split a task

If you need to interrupt work on a task, you can split the task so that part of it starts later in the schedule.

Steps to Split a task
  1. Go to Task Tab in Gantt chart view
  2. Select the task which you want to split [Not summary task]
  3. Click on the “split task” button in the “schedule” group
  4. Then go to Gantt chart and click on the task and drag where you want to drop
Split a task