Trainings

Sunday, November 16, 2014

Formatting Task(s) text in MS Project 2013

Scenario : to emphasis some tasks or make table more readable.
- You can either format individual task or group of tasks .
1. Let say you want to format all the critical tasks background orange.
Steps:
Go to format tab -> Choose Text Styles
Initially dialg box set to change to All text and we have to just change for critical task
so change the "Item to change" to critical task. and then select background color to orange.
In this dialog box One cal also change
  • Font
  • Font style
  • Font Size
  • Font Color
  • underline text
  • Strike through.
That's it. Now click OK.
 
2. Change individual task formating
right click on a task , a pop up will appear , just select the font, style colors etc.