create a Milestone in MS Project 2013

Milestone is used to show key points in the project Production deployment date, customer Approval, Payment date etc.

- Milestone do not have any time duration that is duration column will always have 0

Steps to create a milestone.

1. First select the task where you want to create milestone. e.g. we want to create a milestone above        “Choose new location” task so just select “choose new location”.

2. Go to Task tab then in Insert Section click on Milestone.





Just type the name of the milestone let say “Project Scope Approved.”

We need to link this milestone to show that this task is achieved. e.g. if requirement is reviewed by management and they provide approval in that case “Requirement Approved milestone is approved.”

How to link two task , Please see my tomorrow's post.